Georgia Bids > Bid Detail

Install Fiber Optic Cable for Danis City

Agency: HOMELAND SECURITY, DEPARTMENT OF
Level of Government: Federal
Category:
  • N - Installation of Equipment
Opps ID: NBD00159992768849725
Posted Date: Aug 21, 2023
Due Date: Sep 4, 2023
Solicitation No: 70LGLY23QSSB00128
Source: https://sam.gov/opp/a83770ca62...
Follow
Install Fiber Optic Cable for Danis City
Active
Contract Opportunity
Notice ID
70LGLY23QSSB00128
Related Notice
Department/Ind. Agency
HOMELAND SECURITY, DEPARTMENT OF
Sub-tier
FEDERAL LAW ENFORCEMENT TRAINING CENTER
Office
FLETC GLYNCO PROCUREMENT OFFICE
Looking for contract opportunity help?

Procurement Technical Assistance Centers (PTACs) are an official government contracting resource for small businesses. Find your local PTAC (opens in new window) for free government expertise related to contract opportunities.

General Information
  • Contract Opportunity Type: Combined Synopsis/Solicitation (Original)
  • All Dates/Times are: (UTC-04:00) EASTERN STANDARD TIME, NEW YORK, USA
  • Original Published Date: Aug 21, 2023 05:52 pm EDT
  • Original Date Offers Due: Sep 04, 2023 02:30 pm EDT
  • Inactive Policy: 15 days after date offers due
  • Original Inactive Date: Sep 19, 2023
  • Initiative:
    • None
Classification
  • Original Set Aside: Total Small Business Set-Aside (FAR 19.5)
  • Product Service Code: N059 - INSTALLATION OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS
  • NAICS Code:
    • 238210 - Electrical Contractors and Other Wiring Installation Contractors
  • Place of Performance:
    Brunswick , GA 31524
    USA
Description

Statement of Work



For



Install Fiber Optic Cable for Danis City Expansion Phase II at Glynco, GA



1. Background



This Statement of Work (SOW) establishes and defines the requirements for the engineering,



furnishing, installation, testing and documentation of inside and outside plant fiber optic and copper



cabling at Glynco, GA.





2. Scope of Work



The contractor shall provide all personnel, equipment, tools, materials, supervision, and all other



components necessary to install, test and document inside and outside plant fiber optic and copper cabling



at Glynco, GA. All work performed in the design and installation shall conform to BICSI (Building



Industry Consulting Services International) specifications to ensure consistency with current codes,



standards, and regulations. The following BICSI publications apply. Outside Plant Design Reference



Manual, 4th Edition and Telecommunications Distribution Methods Manual, 12th edition.





3. General.



3.1. Cable Testing. All copper cables will be tested in accordance with BICSI specifications



to ensure no damage has occurred to the cable during installation. All copper cables shall be tested for



cable faults prior to and after installation has been completed. If the cable is damaged during installation,



the contractor shall replace the cable with one that is undamaged. All cable terminals and information



boxes interface units shall be labeled with machine-generated labels. All cables shall be labeled at all



termination points, building entrance terminals, patch panels, manholes, hand holes, and at all splice



entrance/exit points.



3.2. Site Restoration. All non-paved surfaces (grass, sod, gravel, etc.) must be restored within



7 days. Trenches and splice pits must be mechanically compacted to compensate for future earth



settlement. All roads, streets, sidewalks of concrete or asphalt construction must be restored or repaved



within 3 days from the time of backfilling and compaction.



3.3. Grounding. Contractor shall ensure all equipment are secured and grounded to industry



standards.





4. Description of Task



4.1 Task 1: Materials To Install Fiber Optic Cable for Danis City Expansion Phase II at



Glynco, GA



4.1.1. List of materials to be provided by the contractor.



4.1.2. Approximately 4000” of 12 Strand SM Fiber Cable OSP Dielectric



4.1.3. Approximately 4000” of Six Pair, 24 AWG OSP Copper Cable



4.1.4. Four (4) 1U Fiber Shelf (2 Panel) 24/SC or 48LC Patch Panels



4.1.5. Twenty-Four (2$ SC SM Fiber Connector – Hotmelt



4.1.6. Four (4) Fan Out Kit 12 Fiber



4.1.7. Four (4) Bldg. Entrance Protector 06 Pair



4.1.8. #6 AWG Copper Grounding Wire



4.1.9. Cable Tags



4.1.10. Other Materials as needed.



4.2 Task 2: Install Fiber Optic Cable for Danis City Expansion Phase II at Glynco, GA



4.2.1 Contractor shall provide and install approximately 2000’ of 12 Strand Singlemode



Fiber Optic Cable from the Telco Closet of Building 813 (Federal Building) and the



new Training Warehouse building’s Telco Closet. Using existing hand hole and



conduits system.



4.2.2 Fiber Patch Panel using SC-Type Fiber Connectors at both building 813 and the new



training warehouse.



4.2.3 Contractor shall provide and install approximately 2000” of 6 pair OSP Copper cable



between the IT closet of building 813 and the new training warehouse building’s IT



closet, using the existing hand hole and conduit system.



4.2.4 Contractor shall terminate the 6 pair copper cable onto the building entrance protector



terminals in the main Telco closet of building 813 and the traini9ng warehouse IT



closet.



4.2.5 Contractor shall provide and install approximately 2000’ of 12 Strand Singlemode



Fiber Optic Cable from the Telco Closet of Building 813 (Federal Building) and the



new Retail Store Training building’s Telco Closet. Using existing hand hole and



conduits system.



4.2.6 Contractor shall terminate the 12 Strand Single Mode Fiber onto the 1 U Fiber Patch



Panel using SC-Type Fiber Connectors at both building 813 and the new retail store



facility.



4.2.7 Contractor shall provide and install approximately 2000” of 6 pair OSP Copper cable



between the IT closet of building 813 and the new Retail Store Training building’s



Telco Closet, using the existing hand hole and conduit system.



4.2.8 Contractor shall terminate the 6 pair copper cable onto the building entrance protector



terminals in the main Telco closet of building 813 and the new retail training facility’s



IT closet.



4.2.9 Contractor shall ground and label the cable and terminal.



4.2.10 Contractor shall test the cables and provide results to FLETC upon completion.





5 Deliverables



5.2 Equipment



5.3 All equipment identified in 0.1





6 Documents



Item identified in Task 1 and 2





7 Period of Performance.



Period of performance for this contract is not to exceed 90 days from contract award date.





8 Contract Type



This contract shall be a firm fixed price contract.





9 Place of Performance



All Tasks work shall be performed at the Federal Law Enforcement Training Centers; US



Department of Homeland Security; 1131 Chapel Crossing Road, Glynco, GA 31524.





10 Section 508 Requirements (include in the SOW, PWS, or SOO)



Section 508 of the Rehabilitation Act (classified to 29 U.S.C. § 794d) requires that when Federal



agencies develop, procure, maintain, or use information and communications technology (ICT), it shall



be accessible to people with disabilities. Federal employees and members of the public with disabilities



must be afforded access to and use of information and data comparable to that of Federal employees and



members of the public without disabilities.



All products, platforms and services delivered as part of this work statement that, by definition,



are deemed ICT shall conform to the revised regulatory implementation of Section 508 Standards, which



are located at 36 C.F.R. § 1194.1 & Appendixes A, C & D, and available at https://www.ecfr.gov/cgibin/



text-x?SID=e1c6735e25593339a9db63534259d8ec&mc=true&node=pt36.3.1194&rgn=div5. In the



revised regulation, ICT replaced the term electronic and information technology (EIT) used in the



original 508 standards. ICT includes IT and other equipment.



Exceptions for this work statement have been determined by DHS and only the exceptions



described herein may be applied. Any request for additional exceptions shall be sent to the Contracting



Officer and a determination will be made according to DHS Directive 139-05, Office of Accessible



Systems and Technology, dated November 12, 2018, and DHS Instruction 139-05-001, Managing the



Accessible Systems and Technology Program, dated November 20, 2018, or any successor publication.


Attachments/Links
Attachments
file uploads

Contact Information
Contracting Office Address
  • 1131 CHAPEL CROSSING ROAD
  • Brunswick , GA 31524
  • USA
Primary Point of Contact
Secondary Point of Contact


History
  • Aug 21, 2023 05:52 pm EDTCombined Synopsis/Solicitation (Original)

TRY FOR FREE

Not a USAOPPS Member Yet?

Get unlimited access to thousands of active local, state and federal government bids and awards in All 50 States.

Start Free Trial Today >